I have synchronised a Project Pro schedule with SharePoint Online and created a task list. Most of my resource assignment went across but I did have to add some. I found that I had to do this in SharePoint because each time I did this in MS Project I lost
the data. Then I change the mode settings in MS Project for all tasks from Manual to Automatic and I lost all my resource assignments when I synchronised the Project Pro with SharePoint Online. I have cleared the cookies in IE but I still get the problem.
Does anyone have any ideas as to what is causing this?
↧